Work party report 8th December 2024

Work party report 8th December 2024
Richard Dale, Mark Burrows, Jay Hirst and I on were on site. Mark barred the power unit round, oiled the turbos and, with Jay's help, adjusted some of the tarpaulins on Repulse, which had shifted in the high winds the previous weekend. Richard began testing of the warning lights on the rear cab bulkheads, which involved disconnecting...
Continue reading
247 Hits
0 Comments

Work party report 29th September 2024

Work party report 29th September 2024
Dave Rolfe, Mark Burrows, Jay Hirst, Richard Dale and I were on site today. Mark finished fitting rubber strips inside the last of the air filter frame housings, barred round the power unit and oiled the turbos. Dave carried out various jobs around the locomotive. Jay helped Richard doing an endurance test on the internal and extern...
Continue reading
571 Hits
0 Comments

Work party report 1st September 2024

Work party report 1st September 2024
Richard, Dave, and I were on site yesterday. Dave is continuing testing pipework and various valves in the air system of Repulse. He has also mounted the extractor fan above where the ETH generator sits. I fitted and wired the AWS sunflower & reset button in No.2 cab, while Richard finished connecting the two-core cable from the sunflower ...
Continue reading
725 Hits
0 Comments

Work party reports 4th and 18th August 2024

Work party reports 4th and 18th August 2024
Exhauster fitted into place in 50030. Photo by Andy Rowlands.
Dave Rolfe has been putting air into the air system of 50030 at various points, looking for leaks, and inevitably, is finding a lot. He plans to work through the locomotive. This will reveal any more fractured, missing or broken airpipes. I added a new link wire between two terminal bars in No.1 cab as part of completing the unfinished DSD sys...
Continue reading
879 Hits
0 Comments

Work party report 12th May 2024

Work party report 12th May 2024
Andy Rowlands wiring the exhauster speed governor in 50030. Photo by Jay Hirst.
​Dave Rolfe, Jay Hirst, Mark Burrows, Richard Dale, Carl Looker and his daughter Sofy and I were on site today. Mark and Dave were working on the power unit, Carl was de-rusting in the filter compartment of 50030, Sofy was hoovering more debris from under No.1 cab floor. Richard and Jay continued investigating the DSD wirin...
Continue reading
1155 Hits
0 Comments

Work party reports 18th February and 31st March 2024

Work party reports 18th February and 31st March 2024
Mark and Richard were on site on 18th February. Richard reports he did a couple of checks to the cab wiring problems, it appears that we did not have the second live from Cab2 at the Cab1 switch panel, this would explain only having half of the route indicator and no driver's cab light. It seems some of the cab wiring issues is eithe...
Continue reading
1233 Hits
0 Comments

Work party reports 28th January and 5th February 2024

Work party reports 28th January and 5th February 2024
Instrument lighting in the no 1 end cab of 50030 illuminated for the first time in nearly 32 years.
​Richard and I managed to attend for two weekends in a row and together we achieved quite a bit. The new headcode box lamp frame was fitted in No.1 cab, all the internal bulkhead lights had new lamps fitted and the instrument lights in No.1 cab. We were happy with the tests of the lighting circuits at 24v to put the full 110v into them through...
Continue reading
1665 Hits